dpp_02843
AcceptedGPRGGO · Kwinana Green H2 Hub · 09 Apr 2026, 04:00 pm -> 12:00 am
Demo projectKwinana Green H2 Hub uses generated demo data across this dashboard.
Total H2
651 kg
Carbon intensity
1.81 kgCO2e/kgH2
Batches
4
Renewable share
93%
Provenance
- Facility
- Kwinana Green H2 Hub
- Technology
- PEM electrolysis
- Feedstock
- Grid + onsite solar PPA
- Grid factor
- 0.412 kgCO2e/kWh
- Policy engine
- Minviro
- Registry ref
- EDF-048702
Production window
- Window start
- 09 Apr 2026, 04:00 pm
- Window end
- 10 Apr 2026, 12:00 am
- Submitted
- 10 Apr 2026, 12:00 am
- Certificates
- 7 issued
- Intensity
- 15.1 gCO2e/MJ
- Status
- Accepted
Batches in this DPPOpen filtered list
| Batch | Parent DPP | Window | kgH2 | gCO2e/MJ | Records | Status | |
|---|---|---|---|---|---|---|---|
| bch_184707 | dpp_02843 | 09 Apr 2026, 04:00 pm -> 06:00 pm | 185 | 15.7 | 346 | Calculated | |
| bch_184708 | dpp_02843 | 09 Apr 2026, 06:00 pm -> 08:00 pm | 158 | 14.3 | 273 | Calculated | |
| bch_184709 | dpp_02843 | 09 Apr 2026, 08:00 pm -> 10:00 pm | 184 | 15.2 | 251 | Calculated | |
| bch_184710 | dpp_02843 | 09 Apr 2026, 10:00 pm -> 12:00 am | 154 | 14.4 | 312 | Calculated |