dpp_02845
AcceptedUKLCHS · Kwinana Green H2 Hub · 10 Apr 2026, 08:00 am -> 04:00 pm
Demo projectKwinana Green H2 Hub uses generated demo data across this dashboard.
Total H2
760 kg
Carbon intensity
1.76 kgCO2e/kgH2
Batches
5
Renewable share
57%
Provenance
- Facility
- Kwinana Green H2 Hub
- Technology
- PEM electrolysis
- Feedstock
- Grid + onsite solar PPA
- Grid factor
- 0.412 kgCO2e/kWh
- Policy engine
- Minviro
- Registry ref
- EDF-048704
Production window
- Window start
- 10 Apr 2026, 08:00 am
- Window end
- 10 Apr 2026, 04:00 pm
- Submitted
- 10 Apr 2026, 04:00 pm
- Certificates
- 6 issued
- Intensity
- 14.7 gCO2e/MJ
- Status
- Accepted
Batches in this DPPOpen filtered list
| Batch | Parent DPP | Window | kgH2 | gCO2e/MJ | Records | Status | |
|---|---|---|---|---|---|---|---|
| bch_184697 | dpp_02845 | 10 Apr 2026, 08:00 am -> 09:36 am | 134 | 14.1 | 348 | Calculated | |
| bch_184698 | dpp_02845 | 10 Apr 2026, 09:36 am -> 11:12 am | 152 | 14.8 | 350 | Calculated | |
| bch_184699 | dpp_02845 | 10 Apr 2026, 11:12 am -> 12:48 pm | 156 | 14.7 | 269 | Calculated | |
| bch_184700 | dpp_02845 | 10 Apr 2026, 12:48 pm -> 02:24 pm | 153 | 14.8 | 281 | Calculated | |
| bch_184701 | dpp_02845 | 10 Apr 2026, 02:24 pm -> 04:00 pm | 167 | 14.5 | 257 | Calculated |