dpp_02888
PendingGPRGGO · Kwinana Green H2 Hub · 24 Apr 2026, 04:00 pm -> 12:00 am
Demo projectKwinana Green H2 Hub uses generated demo data across this dashboard.
Total H2
695 kg
Carbon intensity
0.72 kgCO2e/kgH2
Batches
4
Renewable share
68%
Provenance
- Facility
- Kwinana Green H2 Hub
- Technology
- PEM electrolysis
- Feedstock
- Grid + onsite solar PPA
- Grid factor
- 0.412 kgCO2e/kWh
- Policy engine
- Minviro
- Registry ref
- -
Production window
- Window start
- 24 Apr 2026, 04:00 pm
- Window end
- 25 Apr 2026, 12:00 am
- Submitted
- 25 Apr 2026, 12:00 am
- Certificates
- -
- Intensity
- 6.0 gCO2e/MJ
- Status
- Pending
Batches in this DPPOpen filtered list
| Batch | Parent DPP | Window | kgH2 | gCO2e/MJ | Records | Status | |
|---|---|---|---|---|---|---|---|
| bch_184474 | dpp_02888 | 24 Apr 2026, 04:00 pm -> 06:00 pm | 162 | 6.8 | 243 | Calculated | |
| bch_184475 | dpp_02888 | 24 Apr 2026, 06:00 pm -> 08:00 pm | 177 | 6.5 | 268 | Calculated | |
| bch_184476 | dpp_02888 | 24 Apr 2026, 08:00 pm -> 10:00 pm | 190 | 5.3 | 353 | Calculated | |
| bch_184477 | dpp_02888 | 24 Apr 2026, 10:00 pm -> 12:00 am | 184 | 6.7 | 247 | Ready |